A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team’s productivity.
What should the project manager do next?
A . Review the iteration duration with the team.
B . Discuss the issue in the next retrospective.
C . Encourage the team to improve their performance.
D . Reduce the iteration backlog.
Answer: B