What should the project manager do next?
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.
%.
What should the project manager do next?
A . Update the assumptions log and change log, and implement the change control process.
B . Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.
C . Inform the client that the project cannot meet the project timeline and additional costs will be incurred.
D . Deliver what was planned in the project management document according to the specifications.
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments