What should the project manager do next?
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project’s schedule and budget .
What should the project manager do next?
A . Perform a qualitative risk analysis and update the risk register.
B . Submit a change request through the Integrated change control process.
C . Update the issue log and discuss It in the next steering committee meeting.
D . Estimate the associated costs and increase the project budget accordingly.
Answer: C