What should the project manager do next?

A project manager identifies a task that will require special knowledge, but none of the team members have this knowledge. The project manager believes a similar situation will occur in an upcoming project

What should the project manager do next?
A . Ask the client to modify the deliverables that require this special knowledge
B . Prepare a training session for the team taking into consideration cost and time.
C . Submit a change request to modify the project scope.
D . Replace members of the team with more experienced individuals.

Answer: B

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments