What should the project manager do next?
A project manager identifies a task that will require special knowledge, but none of the team members have this knowledge. The project manager believes a similar situation will occur in an upcoming project
What should the project manager do next?
A . Ask the client to modify the deliverables that require this special knowledge
B . Prepare a training session for the team taking into consideration cost and time.
C . Submit a change request to modify the project scope.
D . Replace members of the team with more experienced individuals.
Answer: B