What should the project manager do next?
A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
A . Submit a change request to include the manual.
B . Add the needed manual and update the risk log.
C . Review the stakeholder engagement plan.
D . Review the terms and conditions of the contract.
Answer: D