What should the project manager do next?
A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.
What should the project manager do next?
A . Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.
B . Perform quality assurance to review the processes against the quality management plan and identify gaps.
C . Review and update the project document repository with the missing documents and approvals.
D . Change the quality management processes to align with the project objective.
Answer: B