What should the project manager do next?
A project manager prepared the base budget model to deliver a highly customizable software solution. The solution will be delivered in multiple countries with significantly different cultures and will be staged over phases.
What should the project manager do next?
A . Review the base model with the team leaders in each country to establish an independent budget for each phase.
B . Overestimate costs and underestimate revenues to include the impacts of different cultural elements.
C . Apply the company’s operational budgeting model.
D . Ask the project management office (PMO) to review the draft budget.
Answer: A