What should the project manager do next?

While reviewing project documentation, a project manager discovers that modification were made without proper approvals.

What should the project manager do next?
A . Review the requirements management plan.
B . Review the change management plan.
C . Escalate the issue to the project management office (PMO).
D . Escalate the issue to the project sponsor.

Answer: B