What should the project manager do in this situation?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project .
What should the project manager do in this situation?
A . Request the team member to move to another team.
B . Delegate other team members to complete this team member’s tasks.
C . Mentor the team member and provide the necessary training.
D . Include this team member in an improvement program through a human resources request.
Answer: C