What should the project manager do in this situation?

A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.

What should the project manager do in this situation?
A . Schedule a meeting with the reluctant project stakeholder to obtain their feedback.
B. Meet with all seven of the project stakeholders and request all of their feedback.
C. Explain to the sponsor why the reluctant stakeholder needs to provide feedback.
D. Host a meeting with the reluctant stakeholder and project team to resolve any conflict.

Answer: D

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments