What should the project manager do in this phase?

A project manager is developing a project baseline schedule and has started to assign team members to the project activities according to their function .

What should the project manager do in this phase?
A . Develop project onboarding guidelines for the team members assigned to the project.
B . Ensure that a kick-off meeting is planned and invite relevant stakeholders to participate.
C . Ensure that lessons learned are considered as part of the project schedule decomposition.
D . Confirm that no conflicts exist in resource calendars with assigned activities on other projects.

Answer: D