What should the project manager do going forward?
A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.
What should the project manager do going forward?
A . Allocate extra time to inspect deliveries for quality assurance upon arrival at the site
B . Review the contract requirements and ask for the applicable evidence for quality assurance
C . Have the vendor issue the quality documentation prior to the next delivery.
D . Call the vendor and have them verbally guarantee the quality of the next site delivery
Answer: C