What should the project manager do first to resolve this situation?

A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?
A . Update the issue log and escalate to the project sponsor
B . Identify the lack of information as a risk and update the risk register
C . Schedule more frequent meetings with the technical manager.
D . Review and update the stakeholder engagement plan

Answer: B