What should the project manager do first on the agenda?

A project manager holds periodic progress review meetings to discuss issues.

What should the project manager do first on the agenda?
A . Produce lessons learned documentation.
B. Elaborate the risk mitigation strategy and risk register.
C. Formulate project management plan integration.
D. Update resolution approaches and action assignments.

Answer: D