What should the project manager do first?

The team architect resigned from the company. The new architect points out a design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?
A . Review the scope management plan.
B . Update the design with changes.
C . Request an architecture review.
D . Update the quality management plan

Answer: C