What should the project manager do first?

The Change control board (CCB) authorizes two corrective actions for implementation. The first action will cause a delay delivering the regular stakeholder communication report. The second action will require mote man hours on a severely delayed task on a critical path.

What should the project manager do first?
A . Implement the just corrective action, since it was received first
B . Hire an additional resource so that both corrective actions can be implemented simultaneously
C . Implement the second corrective action, since it is on a critical path
D . Ask the CCB for further clarification on its expectations

Answer: C