What should the project manager do first?
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project
What should the project manager do first?
A . Implement the planned risk response to handle the issue.
B . Review possible alternative documentation methods with team
C . Update the risk register with the risk and proposed impact.
D . Ask the team to fix the system to resolve the issue
Answer: D