During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.

What should the project manager do first?
A . Update the issue log and act to minimize the impact
B . Update the schedule to include the delay
C . Add the risk and the delay to the risk register
D . Escalate to the management team for delay approval

Answer: A