What should the project manager do first?
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?
A . Ask upper management for more funds and update the project budget
B . Revise the project scope accordingly to cope with the budget changes
C . Update the risk register and project log. and manage the budget closely.
D . Submit a change request to accelerate the project as requested
Answer: D