What should the project manager do first?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined. The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
A . Share the project documents and invite the key stakeholder to discuss any concerns
B . Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline
C . Proceed with a working session for teams that do not belong to that key stakeholder
D . Invite the key stakeholder to the project’s change control board (CCB) to discuss adjustment of the project strategy
Answer: A