What should the project manager do first?
During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.
What should the project manager do first?
A . Communicate the problem to the sponsor to force the key member to be maintained on the project.
B . Initiate a change request and replace the key member as soon as possible.
C . Explain to the company the importance of maintaining the key member on the project according to the vision of the project.
D . Evaluate the impact of the key team member’s removal from the project, look for alternatives, and submit a change request if required.
Answer: D