What should the project manager do first?
All quality controls have passed, and a project deliverable is ready to be released to the customer However, a change request to add new quality criteria has been approved.
What should the project manager do first?
A . Update the project management plan
B . Stop the release of the deliverable to the customer
C . Use the new quality criteria for future deliverables
D . Update the risk register
Answer: A