What should the project manager do before the project starts?

A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses. The project manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?
A . Ensure that the requirements for the project are understood and that the objectives are verified before approval of an agreement.
B . Inform the project sponsor that once the agreement has been signed, there cannot be any changes to the scope of the project.
C . Notify the project sponsor that the project manager cannot be involved in the agreement negotiation process.
D . Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Answer: A