What should the project manager do as a servant leader?
An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan. The project team evaluated the product’s feasibility of functionality and accelerated testing.
What should the project manager do as a servant leader?
A . Support the team as necessary to find the minimum viable product (MVP).
B . Amend the project budget to include MVP testing
C . Submit a change request to the project sponsor for accelerated testing.
D . Develop the product as per the schedule to perform integration and testing
Answer: A