What should the project manager do about the development team’s request"?
A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches
What should the project manager do about the development team’s request"?
A . Escalate the request for additional financial resources
B . Forward the request to the project management office (PMO) to amend the
organizational process assets
C . Ask the project sponsor to obtain approval for implementation of the new approach
D . Analyze the requirements that will need to be addressed under the requested method
Answer: B