What should the project manager do?
During the review of a project’s list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed .
What should the project manager do?
A . Check the approved list of requirements to see if there are any missing items.
B . Work with the stakeholder to improve the requirements’ acceptance criteria
C . Review the requirements traceability matrix with the concerned stakeholder
D . Discuss with the stakeholder which additional requirements should be added
Answer: C