What should the project manager do?
Members of a project learn are based in two countries Experienced resources work together at company headquarters in country A, while the remaining resources who deliver the project work, are located in the client’s office in country B. The project manager is located in the client’s office most of the time Last month, the experienced resources discovered several unacceptable issues, and expressed concern that the project manager is unable to fairly evaluate all efforts This causes the experienced resources’ productivity and morale to decline
What should the project manager do?
A . Ask the experienced resources to recommend solutions to the issues
B . Spend more time with the experienced resources to better support them
C . Review individual achievements, and share them more frequently with the entire project team.
D . Review personal goals with the experienced resources, and realign them with project needs and execution
Answer: C