What should the project manager do?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.
What should the project manager do?
A . Determine the risks and identify a resolution during the retrospective meeting
B . Inform stakeholders about the delay during project updates
C . Determine cross-dependencies and plan a spike in the next spont
D . Discover the gaps in the communications management plan and address them accordingly
Answer: A