What should the project manager do?

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?
A . Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome
B . Update the communications management plan and implement the change
C . Meet with the project sponsor to discuss how to address the situation.
D . Meet with the stakeholder prior to the meeting to obtain their opinion

Answer: D