What should the project manager do?

The construction process for a building project is complete and the project manager wants to dose the project Some team members are already assigned to a new project. The remaining team members are unsure about what to capture in the close-out report.

What should the project manager do?
A . Complete the report using the lessons learned from a similar, previous project.
B . Conduct the project close-out work with the remaining team members and solicit input from the reassigned members
C . Forego the lessons learned meeting and complete the task independently.
D . Hand over the project close-out phase to the project manager working on the new project

Answer: B