What should the project manager do?

In a software development project, the product owner and development team agree on a sprint backlog. The highest priority in the backlog is to build a payment module. The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.

What should the project manager do?
A . Let the developers focus on the refactoring work and discuss it in the retrospective
B . Restate to the developers the importance of focusing and meeting the sprint goal.
C . Praise the developers for their proactivity and focus on quality.
D . Escalate the issue to the developers’ functional managers

Answer: A