A company is going through a reorganization Although not all new positions are known yet organization changes are already being communicated.
What should the project manager do?
A . Update the stakeholder register with the information that is already.
B . Align expectations with key stakeholders.
C . Update the risk management plan with potential future stakeholders.
D . Inform all stakeholders about the current project status.
Answer: A