What should the project manager do?

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints .

What should the project manager do?
A . Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project
B . Provide an incentive plan so the team members will work more unaccounted hours on multiple projects
C . Brainstorm with the team members on how they can deliver on multiple projects within the given budget
D . Instruct the team members to spread evenly across projects so mistakes will not occur
within the current budget.

Answer: B