What should the project manager do?
A project manager is working with an agile team. A key stakeholder who does not join the sprint planning session is very unhappy, as the delivery date for the final product has been pushed back three times .
What should the project manager do?
A . Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.
B . Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.
C . Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.
D . Secure some additional funding to recruit more resources to the project team to enable faster delivery.
Answer: A
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund