What should the project manager do?
A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis. The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?
A . Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team
B . Escalate the issue to the functional manager
C . Help the team member to perform the quantitative risk analysis through coaching, mentoring and training
D . Perform the quantitative risk analysis for the team member.
Answer: C