What should the project manager do?

The main project stakeholder was fired and replaced by another stakeholder. The new stakeholder reviewed the project scope and requested numerous changes, arguing that the stakeholder’s team is unhappy with the results to date.

What should the project manager do?
A . Put the new requirements in the backlog with high priority and implement the requested changes.
B . Put the new requirements in the backlog and submit a formal change request for approval.
C . Put the new requirements in the backlog and let the product owner check their value and priority.
D . Put the new requirements in the backlog with low priority and implement the requested changes.

Answer: C