A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted
What should the project manager do?
A . Request stakeholders who understand the technology.
B . Recommend a change in technology to senior management.
C . Plan to conduct informal sessions with the stakeholders.
D . Include the issue in the Issue log and escalate to senior management.
Answer: A