What should the project manager do?

A key resource is newly assigned to a project. The project manager and the resource did not get along well in a previous project. This resource is needed to ensure the completion of a major component for the project.

What should the project manager do?
A . Work on resolving the differences with the key resource and building a good working relationship to ensure project success.
B . Monitor the key resource closely throughout the project, but do not let the project sponsor know about the conflict.
C . Request that the key resource’s functional manager work directly with the resource during the project.
D . Discuss this with the project sponsor and request that this key resource be replaced on the project.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments