What should the project manager do?
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned .
What should the project manager do?
A . Check with the team to learn what can be done, and consult an expert
B . Ask the sponsor to close the project and pay the contracted penalty.
C . Check that this information was documented correctly
D . Meet with the sponsor to ask for their support
Answer: A