What should the project manager do?
A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task
What should the project manager do?
A . Ask the team member to follow the approved communications management plan to communicate their issue
B . Schedule a meeting with the concerned team member to review and update the issue log together
C . Review the risk register with the team member to find the proper response action for this issue.
D . Ask the team member to raise a change request to assess the issue in detail
Answer: B