What should the project manager do?

An international client contacted a software development company to build out a software product, and an agile project manager was assigned. At one of the review meetings, the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?
A . Include the mentioned feature in the prioritized requirements list.
B . Assign a team member to immediately start working on that feature.
C . Review the original project documentation to confirm.
D . Treat it as a change request and assess the effect on the project’s goals.

Answer: C