During a product’s testing phase, the customer discovers that a previously identified defect remains unfixed.
What should the project manager do?
A . Review and update the issue log
B . Identify and discuss corrective actions with the team
C . Assign a team member to fix the issue
D . Update the risk register
Answer: A