What should the project manager do?
A project manager is working with an agile team. A key stakeholder who does not join the sprint planning session is very unhappy, as the delivery date for the final product has been pushed back three times.
What should the project manager do?
A . Meet with the stakeholder to understand the concern and business impact, reprioritize as necessary, and invite them to join the sprint planning session.
B . Direct the product owner to drop other work in progress and work on this stakeholder’s requirement as the top-priority item.
C . Share the prioritized items that the team is working on with the stakeholder and invite them to join the sprint planning session.
D . Secure some additional funding to recruit more resources to the project team to enable faster delivery.
Answer: A