What should the project manager do?

The project manager is experiencing delays with two critical tasks that are to be executed by two different teams. The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?
A . Arrange a meeting with the managers and try to reach an agreement.
B . Communicate with the project sponsor regarding the need to resolve the conflict between the managers.
C . Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan
D . Meet with both teams and their managers and try to figure out the root cause of the conflict

Answer: D