What should the project manager do?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
A . Create a training schedule for the new team member to follow over the next few weeks.
B . Escalate the inquiry to the team member’s functional manager.
C . Clarify the relevance of reviewing the documentation on the intranet.
D . Ask a senior team member to help the new team member navigate through all the documentation.
Answer: C