A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus.

What should the project manager do?
A . Ask the product owner, who is the key stakeholder, to choose among the different ideas.
B . Propose ideas to the group, ask everyone to vote, and then choose the most popular idea
C . Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.
D . Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Answer: C