Provisional training is provided for a project that is in the process of client hand-over. The client then asks for a step-by-step manual which was not included in the project’s deliverables

What should the project manager do?
A . Accept the request and have the learn immediately begin work on the manual
B . Initiate the change control process
C . Offer to develop the manual as a separate project
D . Reject the request because it is out of scope

Answer: C