A project team’s performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting.

What should the project manager do?
A . Focus on remediation not merely on correcting symptoms
B . Compare the team’s performance against other project teams
C . Identify potential failure points based on the iteration workload
D . Motivate the team to perform better

Answer: C