What should the project manager do?
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies
What should the project manager do?
A . Make sure the project team is aware of all agile techniques
B . Skip the training because the team already understands agile
C . Ensure the team has a common understanding of agile
D . Teach one agile methodology fully and completely
Answer: C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments