What should the project manager do?

A project manager discovers an enhancement that will improve the design being developed by a subject matter expert (EME).

What should the project manager do?
A . Disregard the enhancement, as no changes are allowed.
B . Ask the expert to implement the enhancement.
C . Ask the change control board (CCB) to review the enhancement.
D . Document this discovery, and present it to all stakeholders.

Answer: D